08/21/03
Today we had a walk-thru with our
Builder. Everything is pretty much complete. We only found minor
problems with the house and they are still working on our landscaping.
We will have our Final walk-thru next week. New pictures in the photo
gallery. The blue tape in the photos are to mark where they need touch
up paint or repair.
08/11/03
Sod and landscaping complete. The
landscaping is all wrong so look for updates later this week.
Fence is complete. Mirrors and sinks are in.
08/06/03
Appliances have been installed, Inside
speakers are complete, The fence is up, the security cam is installed,
Door knobs and wall plate covers have been installed.
08/02/03
Light Fixtures, and sinks have been
installed.
07/31/03
Kitchen Counters and Bathroom Counters
are installed, Marble has been installed around the fireplace, Tile
entry way is complete, Kitchen Floor is complete, Gutters are complete,
Driveway and Patio are poured, Front door is painted, Stair posts have
been stained to match the kitchen cabinets.
07/26/03
Brick is Complete, Cabinets have been
installed, Inside Painting has begun.
07/21/03
Drywall is completed, Kitchen and
Bathroom cabinets have been delivered. Only the front of the house is
left to brick.
07/16/03
Drywall is almost Complete, Brick work
has started on the back and sides of the house.
07/08/03
Pre-Dry Wall meeting is over. We have
plumbing, electrical fixtures and are wired for surround sound and our
security camera.
06/27/03
We have a Roof and heat and air duct
work.
06/22/03
Frame Started
06/18/03
Foundation Poured
06/04/03
Uploaded floor Plan Pictures to the Photo Gallery
5/31/03
Rough plumbing started
5/24/03
Forms are set and trenches are dug in prep for rough plumbing.
05/20/2003
The Lot has been cleared